Water Course Crossing Methods
For Northern Gateway, the following construction methods may be used for water course crossings:
Isolation Method
- The work area is isolated from the flow of the stream and the pipeline is installed in dry conditions
Trenchless Method
- Includes horizontal directional drill, “bore” microtunnel and aerial options
- Construction of the crossing and installation of the pipeline has little impact on the stream itself
- Streams that have high flows during construction and/or high fisheries sensitivity may be crossed this way
Open Trench Method
- Occurs without any isolation or diversion of flow away from the work area
- Streams that cannot be crossed using the other methods may be crossed this way
- Any stream that is dry or frozen to the bottom will be crossed with this method