Pipeline Construction
Construction of Northern Gateway will be divided into segments, or spreads, to break the work into manageable sizes for the winter and summer construction periods.
- It is expected that 12 construction spreads will be required
- Construction spreads will range in length between 70 km and 190 km
- The number of construction spreads may change as more engineering and environmental details become known
Pipeline construction typically has five major phases:
1. Preparing the right-of-way
2. Grading the right-of-way
3. Pipeline installation
4. Cleaning and testing
5. Clean-up and restoration
- Preparing the right-of-way
This work involves clearing vegetation from the right-of-way
- Certain vegetation, such as market-quality timber, is salvaged
- Other vegetation, such as woody debris, is either cleared or used to create controlled access points
- Temporary access to and along the right-of-way is established, including the installation of bridges at stream crossings to accommodate construction vehicles
- Grading the right-of-way
This work generally involves removing and stockpiling the topsoil, and blasting and removing large rocks from the route.
- Emphasis is on environmental conservation and salvaging topsoil
- Grading on Northern Gateway’s right-of-way will be limited, but is required along portions of the route to safely accommodate pipe installation and equipment travel
- Pipeline installation
This work involves stringing, pipe welding, installing, trenching and backfilling activities.
- Stringing is when individual pipe sections are laid end-to-end – individual pipe joints are bent to fit the terrain and then welded together to form long “strings”
- Welds are inspected using X-ray or ultrasonic methods
- Pipeline joints are coated and re-inspected
- Trenching is completed and the pipe is gently lifted and laid, generally to a depth of a metre or more beneath the surface, and then the trench is backfilled
- Cleaning and testing
Once the pipeline is installed, it is cleaned thoroughly and pressure-tested using water and air.
- Water is pumped through the pipeline at a higher level of pressure than when operational to ensure the integrity of the pipe
- The same testing is also conducted with air
- Clean-up and restoration
The final phase includes closing off all temporary construction access, replacing topsoil, and installing cross-beams and surface water control.
- Land and water crossings are restored
- Because the land is rebuilt to exacting standards, right-of-ways can usually be used as they were prior to the construction